EPC contract by BPDB for setting up two HFO fired power plants (100 MW in Gopalganj & 50 MW in Faridpur).

Being the first ever local company, Energypac had been awarded with EPC (Engineering, Procurement & construction) contract by BPDB for setting up two HFO (Heavy Furnace Oil) fired power plants (100 MW in Gopalganj & 50 MW in Faridpur) through international bidding. On 31st December 2011, Honorable Prime Minister, Sheikh Hasina inaugurated the 108.95 MW power plant at Gopalgonj unveiling the curtain on stone in Sheikh Kamal Stadium, Goplagonj at 3.00pm.

With the implementation duration of 450 days, the Gopalgonj power plant was commissioned on 29th August 2011. The plant has started its commercial production on 16th November, 2011. Mr. Rezwanul Kabeer, Director, Energypac Power Generation Ltd. presented the project model to Honorable Prime Minister.


Gopalganj 100 MW Peaking Power Plant at a Glance

Name of the Project : Gopalganj 100 MW Peaking Power Plant
Implementing Authority : Bangladesh power development Board (BPDB)
Place : Haridaspur, Gopalganj
Type of fuel to be used : HFO fired
Total Guaranteed Capacity : 108.95 Mwe
Contract Signing Date : 26th April, 2010
EPC Company : Energypac
Contracted value : 6.9308 bTk (99 mUSD)
Financed by : Standard Chartered Bank
Implementation Time : 450 Days
COD : 29th August, 2011
Source of Fund : Government of Bangladesh

Faridpur 50 MW Peaking Power Plant at a Glance

Name of the Project : Faridpur 50 MW Peaking Power Plant
Implementing Authority : Bangladesh power development Board (BPDB)
Place : Faridpur
Type of fuel to be used : HFO
Total Guaranteed Capacity : 54.47 Mwe
Contract Signing Date : 26th April, 2010
EPC Company : Energypac
Contracted value : 3.83 bTk (54 mUSD)
Financed by : HSBC
Implementation Time : 450 Days
COD : 18th August, 2011
Source of Fund : Government of Bangladesh
 
 
 
 
 
 
 
 